The work wasn’t in 4 stages, the payments were. There was a contract/invoice that I was sent that set that out and the third payment was due at the completion of the exterior of the extension (which it is not).
The name of the Contractor is Tim Wise and his company is TJW Projects.
i have asked the Council to confirm the details of their visit in writing.
i had already told Tim that I was not happy with several aspects of the work, he had said he was going to but these were things that I could see like the tiling, plastering, carpentry, not the structure of the building, building control have only just been round a week after I last saw the contractor or any other work done. Luckily I had taken photos which I showed them and along with what they have seen have said it needs taking down. I had told Tim in an email that they would be coming.