Hi all,
I will try and make this as brief as possible.
I am currently getting a brick porch built it is 2/3 built. The price was agreed before building work commenced at £5,700.
During the build i changed the plans for the roof before work on the roof had started, from a pitched roof to an hipped roof. I requested the extra cost for the roof on 6th August but did not receive the updated cost until work on the roof was close to completion.
After several requests for for the amended price, i finally received an updated price on the 31st August.
The final price of the build on the 31.08.19 is now £10,000. The additional cost of the hipped roof was £1,400 . However in the exchange of emails the builder has ACCEPTED liability that he miscalculated the size of the porch by adding the length and depth of the porch instead of multiplying. Therefore, this means that the materials for the bricks, cement, footings and labour for all ground works and brick layering, have all been miscalculated by in the builders quote.
Subsequently, in the last 48 hours, i have now had 5 different quotes off him.
1 - 10,000
2 - 8,900
3 - 11,000
4 - 9,100
5 - 8,300
I have rejected all of these, as i do think i should be liable to pay for his incompetence regards to miscalculating the size of the build.
I asked him the question if i had not changed the plan for the roof and the porch was built as planned with a pitched roof for £5,700, would you now be asking me for more money. His reply was yes due to miscalculating the size.
For a quick solution i offered £7,500 for the completed build which i believe is reasonable but he has rejected this but would accept £8,300.
Estimated build time was 2 weeks, we are now into the 9th week.
I believe i am in my right to stand firm as he as accepted liability.
Any feedback would be appreciated.
Thanks